I seem to find a lot of different opinions on fixing walk-in shower trays to floors. I will be fixing to a marine ply base screwed into joists with noggins. The manufacturer says bed into a weak mortar mix, but I read that this can lead to problems when the mortar dries out. Some say silicon, some say low expansion foam, some say tile adhesive, some say mortar.

What is the definitive way to fix a shower tray?
 
I think you will always get a few different opinions on the best method. However we always use tile adhesive and have never had an issue or call back over a failed tray.
As you stated make sure it is on one piece of ply, if necessary overlap the ply to make sure it is solid. Prime the wood the night before and then set on 5mm to 10mm adhesive bed. 24hrs later it should should good to go.
One of the biggest problems we find is that everyone is going for large trays and they are rarely flat and true. Always make sure the edges that the enclosure sits on are level and you should be fine.
 
Is the tray fully level on the bottom or is there a few indents etc ?
 
Mortar mix or tile adhesive (mortar based) wouldn't recommend anything that's too sticky or has any flex incase it moves or ever has to come out.
I wouldn't be happy trying to strip out a tray stuck with silicone or contact adhesive!
 
I always expanding foam them. Not everyone agrees, but never been called back to one or had any issues over the years.

It's great as it fills in all the hollows underneath the tray, and they grab like ****. They're solid after it's gone off.
 
Sand a cement required then as it will fill in all the gaps

I know if you use the leg kits they normally only span normally a 4” circle but manufacturers say that’s fine somehow but when it’s beaded down it needs full coverage 🤔
 
I always use a good quality flexible tile adhesive as others have mentioned prime well with SBR before bedding down never had a issue doing it this way . Kop
 

Attachments

  • IMG_20201015_104157.jpg
    IMG_20201015_104157.jpg
    666.6 KB · Views: 23
  • IMG_20201015_122732.jpg
    IMG_20201015_122732.jpg
    373.6 KB · Views: 21
  • IMG_20201023_181322.jpg
    IMG_20201023_181322.jpg
    299.4 KB · Views: 23
Thanks all, I think I'll use mortar to comply with the guarantee. I like the idea of the low expansion foam though, I've heard you should 'decouple' the shower tray by squirting the foam down, then laying a thin polythene sheet over the foam, then the shower tray on top. That way it's not a nightmare to replace if something does go wrong.
 
I did a shower once, did a proper job, boarded and everything, set on screed, backer boards etc.
The bottom row of tiles kept cracking at grout line. After several return visits we concluded that as the fella was built like Thor and well over 20st it was the joists flexing?
Not sure what I'd have done about that but it wouldn't have been to set it in foam!
Eventually customer moved and I heard no more about it
 
So I finally installed the shower tray on a bed of 5:1 mortar. Levelled it then weighed it down with 200kg of weight, and left for 24 hours. Upon inspection next day, the base of the shower tray is rock solid, but I can still see a mm or two of flexing at the edges. Extremely annoying but is this anything to worry about?
 