Got called to an emergency where an old style double panel radiator (the heavy type) had been screwed to a stud wall, over the years it had worked loose of the plaster board screws and all of a sudden just dropped off, turned up customer had pushed some heavy furniture against it to keep it in place. Furniture was removed and pipes promptly burst, I got wet, plugged split pipe (with a pencil and PTFE!!!) and drained down. Just priced up the replacement for them including the two hours of wetness I went through and wondered if you thought this price was reasonable;
1 Single panel Radiator (4083 BTU)
Rad Valves
Pipe work alteration as they had to be capped in the cavity wall (pipe and associated fittings)
x200 inhibitor
4hours labour (including initial getting wet call out)
336.22 Total job price
I've priced it according to how much my materials will cost and to how much I charge per hour, but just wondered what you all thought for the price.
Thank you once again in advance
Foodface
1 Single panel Radiator (4083 BTU)
Rad Valves
Pipe work alteration as they had to be capped in the cavity wall (pipe and associated fittings)
x200 inhibitor
4hours labour (including initial getting wet call out)
336.22 Total job price
I've priced it according to how much my materials will cost and to how much I charge per hour, but just wondered what you all thought for the price.