P
peter4321
Hello,
I'm having a 'little' dispute with my builder, mainly over his project management. I think his bizarre scheduling has meant we paid way over the odds for plumbing services - and ended up with something a bit rubbish.
We've had a ground-floor extension built so the back room is now three metres longer than it used to be. And we've got two new radiators, one each side of the room, near the new back of the house.
Problem was that the concrete floor was poured (and the walls were plastered) before the plumbers came to install pipes for the radiators. So the plumbers ran the pipes along one wall, then dug a trench through the new concrete to reach the other wall, then ran pipes along there.
It then took quite a lot of self-levelling compound to sort out the floor over several days. And my skirting boards are about 90mm thick to conceal the pipes.
Is this normal? Or should the pipes have gone across the floor before the concrete was poured? And should they have gone into the wall blocks before it was plastered?
Would be nice to check if he messed up before I start throwing accusations around...
Thanks very much,
Peter
I'm having a 'little' dispute with my builder, mainly over his project management. I think his bizarre scheduling has meant we paid way over the odds for plumbing services - and ended up with something a bit rubbish.
We've had a ground-floor extension built so the back room is now three metres longer than it used to be. And we've got two new radiators, one each side of the room, near the new back of the house.
Problem was that the concrete floor was poured (and the walls were plastered) before the plumbers came to install pipes for the radiators. So the plumbers ran the pipes along one wall, then dug a trench through the new concrete to reach the other wall, then ran pipes along there.
It then took quite a lot of self-levelling compound to sort out the floor over several days. And my skirting boards are about 90mm thick to conceal the pipes.
Is this normal? Or should the pipes have gone across the floor before the concrete was poured? And should they have gone into the wall blocks before it was plastered?
Would be nice to check if he messed up before I start throwing accusations around...
Thanks very much,
Peter