P
Pea
I had a heating engineer install a Vaillant boiler on 23rd August 2012, I didn't realise at the time but he was supposed to commission the boiler and supply us with the benchmark etc but he didn't. We have asked him to come back numerous times to take the necessary tests (which he says he needs to do) so that he can provide the paperwork but he keeps saying he will give us a date to attend but never actually gives us a date.
Can you advise me where we stand and how we can get him to come back and take the tests etc?
:annoyed:
Can you advise me where we stand and how we can get him to come back and take the tests etc?
:annoyed: