Hi folks,
I'm a bit concerned with what the Gas Transporter is proposing regarding a replacement pipe install to the properties in the close I live on. The demographic is predominantly elderly, but it seems to be the contractors have gone a bit kamikaze & seem obsessed with finishing early rather than doing a proper neat job.
Basically, the roads/pavements have been already dug with varying degrees of accuracy, with the feed to a nearby street lamp severed by their digger, leaks in water mains (digger again) & uneven driveways where the mini-digger's bucket has been used to break up concrete, causing the residents to be upset with the standard of work.
That aside, the holes have been dug but we're all awaiting the change of pipe from supply to meter, and I was wondering if anyone could please answer a couple of queries on behalf of the residents, mainly regarding the location of inlet pipes and meters.
Most of the houses are of similar construction.
The 'old' pipes currently go through the outer wall on an above-ground inlet but below the DPC, and most meters are located on the inside of garages but against the outer walls.
The queries re this ^ would be:
a) Is an above-ground inlet below a DPC for existing properties now considered 'against regs' for renewing, as the holes already exist & it seems daft to drill through again, especially considering most have had rendering added from DPC upwards.
b) If the Transporter's inlet pipe has to be above DPC, is there a lower and upper limit for siting of the inlet pipe to comply with regs?
There's also mention by the contractor of a 2 metre maximum on the amount of copper piping used from T-junction inlet/ECV to Gas meter, with an additional caveat half a metre is 'taken off' for each bend in the piping, including the T-junction inlet and effectively making the maximum height of meter from the inlet 1 metre.
Would this be correct?
As a result of this ^, the Transporters' contractor is currently suggesting either the outside pipe is extended to eye level on the outside of properties to match the existing positioning of meters behind the outer wall (like the pole on a Routemaster), or the meter must be moved to nearer the T-junction inlet, almost at knee level.
Apparently, one member of their team is a stickler for the 2 metre copper piping rule (meaning in most cases the meter has to move to the T), whilst another member of the team couldn't give a flying one!
It all seems pretty bizarre & random & doesn't seem right. It doesn't help getting different answers from different members of their team, but any advice would be appreciated as I want to try and help the residents avoid unsightly piping on the exterior of their houses, some of which have been located right next to their front doors...
Thanks in advance 🙂
I'm a bit concerned with what the Gas Transporter is proposing regarding a replacement pipe install to the properties in the close I live on. The demographic is predominantly elderly, but it seems to be the contractors have gone a bit kamikaze & seem obsessed with finishing early rather than doing a proper neat job.
Basically, the roads/pavements have been already dug with varying degrees of accuracy, with the feed to a nearby street lamp severed by their digger, leaks in water mains (digger again) & uneven driveways where the mini-digger's bucket has been used to break up concrete, causing the residents to be upset with the standard of work.
That aside, the holes have been dug but we're all awaiting the change of pipe from supply to meter, and I was wondering if anyone could please answer a couple of queries on behalf of the residents, mainly regarding the location of inlet pipes and meters.
Most of the houses are of similar construction.
The 'old' pipes currently go through the outer wall on an above-ground inlet but below the DPC, and most meters are located on the inside of garages but against the outer walls.
The queries re this ^ would be:
a) Is an above-ground inlet below a DPC for existing properties now considered 'against regs' for renewing, as the holes already exist & it seems daft to drill through again, especially considering most have had rendering added from DPC upwards.
b) If the Transporter's inlet pipe has to be above DPC, is there a lower and upper limit for siting of the inlet pipe to comply with regs?
There's also mention by the contractor of a 2 metre maximum on the amount of copper piping used from T-junction inlet/ECV to Gas meter, with an additional caveat half a metre is 'taken off' for each bend in the piping, including the T-junction inlet and effectively making the maximum height of meter from the inlet 1 metre.
Would this be correct?
As a result of this ^, the Transporters' contractor is currently suggesting either the outside pipe is extended to eye level on the outside of properties to match the existing positioning of meters behind the outer wall (like the pole on a Routemaster), or the meter must be moved to nearer the T-junction inlet, almost at knee level.
Apparently, one member of their team is a stickler for the 2 metre copper piping rule (meaning in most cases the meter has to move to the T), whilst another member of the team couldn't give a flying one!
It all seems pretty bizarre & random & doesn't seem right. It doesn't help getting different answers from different members of their team, but any advice would be appreciated as I want to try and help the residents avoid unsightly piping on the exterior of their houses, some of which have been located right next to their front doors...
Thanks in advance 🙂
Last edited: