Hi
I’m after some advice about the pipework for my loft conversion.
I am having a bathroom on the right side of the loft and the waste will need to run through all of the floor joists (red line) to pick up the stack which is on the gabel end.
My question is can I drill through all these joists and still meet building regs ? I can’t see any other way of running the waste for the shower and basin as I want the shower sitting on the floor.
Due to length of run being over 3 meters it should be run in 2 inch but will 11/2 suffice ?
Thanks
I’m after some advice about the pipework for my loft conversion.
I am having a bathroom on the right side of the loft and the waste will need to run through all of the floor joists (red line) to pick up the stack which is on the gabel end.
My question is can I drill through all these joists and still meet building regs ? I can’t see any other way of running the waste for the shower and basin as I want the shower sitting on the floor.
Due to length of run being over 3 meters it should be run in 2 inch but will 11/2 suffice ?
Thanks