i doubt if i could do it now but we used to do 7 rads and boiler 2 days for two of us small house are often harder than bigger places as theres nowhere to shove the furniture
i think our record was 8rads and boiler in a day four floors back to back rads and surface verticals looked a treat lol
 
Okay so would I be right in saying it would cost more than the average price guide of £3k due to the type of house. Only thing I am thinking about now is how are the radiators going to be fixed to the wall as they are stud walls.

it should not cost much more than a standard house type, aslong as the walls are solid the rads could be fitted on heavy duty toggles. The boiler may need to have a stud fitted inside the wall and an non conbustable board between its self and the wall to keep fire ratings.
 
Have done loads of these houses steel framed prefab houses as already stated straight up into loft and on drops in out in a day £600 labour 2x plumbers and labourer start 8 finish 4p.m and as good as any install thats taken a week all flushed clipped etc etc
 
Have done loads of these houses steel framed prefab houses as already stated straight up into loft and on drops in out in a day £600 labour 2x plumbers and labourer start 8 finish 4p.m and as good as any install thats taken a week all flushed clipped etc etc

really ?
 
I used to work with 2 welsh guys a few years back, we used to do a full heating, most times a combi and at least 8 usually 10 rads, trunking vertical and horizontal, bay windows too. All done and dusted for about 3 everyday. You can be quick and neat, if its something you do for long enough you build up the speed without loosing the neatness.
 
Yep spent years doing heating systems in a day , 2 plumbs and labourer on same routine gets to be a doddle to such an extent we were doing two packs a day at one point .
Absolutely creamed it in , all water samples passed as well which seems to be rarity now
 
The heating is on and flushing while all the patching and paperwork is being done, so about 1.5 hours. No it aint being flushed for 2 hours as it says it should be, but I bet not 1 off the guys on here ever do that.
We had to take samples in Sentinel tubes for company, so all cleaned and inhibited.
 
Last edited:
i flush my new installs correctly including taking tds readings, but thats what i have charged for i guess. I have seen hundreds of one a day installs, put plenty of them right aswell.
 
how long do you spend flushing and commissioning in this day?

i usually only do a cold water flush anyway tryed the powerflushing root never made any diffrence and just took up time ,if the systems that bad the rads with be nacked anyway so i always say change them or i walk away as just gunner have loads of call backs and hassle i flush out with mains pressure then put cleaner in for a week then go back empty the system then put inhibitor in ,as well as a tf1 on the system works fine for me
 
Oh dont worry those days have gone for me as well !!
like most i spend time up the merchants waffling about how a few year ago i was home by two with £250 in the bank each day no lucky if i get fifty quid lol
 
Yep spent years doing heating systems in a day , 2 plumbs and labourer on same routine gets to be a doddle to such an extent we were doing two packs a day at one point .
Absolutely creamed it in , all water samples passed as well which seems to be rarity now

Two full systems in a day? There is no way that would be a good standard of work in my eyes.
 