Scott_D

Esteemed
Plumber
Gas Engineer
Subscribed
Nov 20, 2012
6,128
2,736
113
BRISTOL
I am pricing a house refurb and could use a little help on the price

Large old terraced
It will have 6 bedrooms and 4 bathrooms
System boiler and 300 ltr unvented
9 Rads and 4 Towel rails
Hot and cold into the bathrooms (builder to do the bathrooms)

Around £4000 materials
Im thinking £3000 labour
I could do with the work but I dont want to end up earning next to nothing
 
Maybe day rate ??
Just priced job agreed day rate and they pay materials. Needed the work and it worked well for both of us
 
  • Like
Reactions: Scott_D
I am pricing a house refurb and could use a little help on the price

Large old terraced
It will have 6 bedrooms and 4 bathrooms
System boiler and 300 ltr unvented
9 Rads and 4 Towel rails
Hot and cold into the bathrooms (builder to do the bathrooms)

Around £4000 materials
Im thinking £3000 labour
I could do with the work but I dont want to end up earning next to nothing
Are you just installing the cylinder and boiler?
Is there a new gas run required?
How much pipework is required?
 
around 10k

just done one all in around 2 months

400l cylinder
worcester 162
7 bathrooms

around 12-15k that was as builder supplied the big items eg boiler and cylinder
 
You need to remember you have to plumb, hot and cold to all bathrooms, full central heating, lagging, flushing, installing boiler and cylinder, wiring, perhaps a water softener etc ... it’s a lot of work
 
  • Agree
Reactions: king of pipes
Have you had to give an accurate number of days?

No never just said I will be on site 9 till 4.30 and have rolling dinner. Said quite happy for them to keep tabs on me also by the materials going in will tell you in working. They had quotes tho so had a good idea of timescale.
 
  • Like
Reactions: Scott_D
Just quoted on a 5 bed three bathroom refurb 40kw boiler , 250 litre unvented cylinder basic sandringham sanitary ware one walkin shower, one cloakroom all new pipework hot colds, gas, water rads upstairs underfloor on the ground floor, all copper install estimate was £12,000 labour and minimum £12,000 materials as could change , it doesn't take longer to rack up the hours on site 2 men 80 hours a week is £1500 - £1800 a week 6 weeks was my reckoning x 2. Kop
 