andrew2000
Scenario...
- CI soil pipe on outside wall (1948), neighbour shared, combined foul & storm
- Saniflo some 3.2m from the outside wall, 22mm piping assumed.
- Flooring grade Asphalt, Screed of unknown thickness (1948), Concrete Raft - rebar assumed to be >70mm down.
- Saniflo 22mm outlet pipe fall 1:200 most likely, 1:100 is a bit skimpy re risk of solids buildup
It might be possible to diamond saw the FLOOR for the 3.2m with sufficient coverage for flex conduit and plastic coated 22mm pipe.
Floor level is about 2-2.5 bricks above ground outside.
CI soil pipe has no bottom socket visible.
So does that mean the rest bend is separate (socket below ground) or integral?
Under BR AD H the lowest point for a 22mm boss connector is 450mm above the invert of the rest bend. I hunted last night for some other restriction, but that does appear to be it.
I could lift a 3x2 and trowel away at the clay until I find the pipe, however this is still at the "all possible on the shelf designs" stage. The low level brick manhole cover could have a 22mm low entry, but that part would be outsourced (paved cover, waterproof pipe insulation, UV proof also above terra firma).
Thanks.
- CI soil pipe on outside wall (1948), neighbour shared, combined foul & storm
- Saniflo some 3.2m from the outside wall, 22mm piping assumed.
- Flooring grade Asphalt, Screed of unknown thickness (1948), Concrete Raft - rebar assumed to be >70mm down.
- Saniflo 22mm outlet pipe fall 1:200 most likely, 1:100 is a bit skimpy re risk of solids buildup
It might be possible to diamond saw the FLOOR for the 3.2m with sufficient coverage for flex conduit and plastic coated 22mm pipe.
Floor level is about 2-2.5 bricks above ground outside.
CI soil pipe has no bottom socket visible.
So does that mean the rest bend is separate (socket below ground) or integral?
Under BR AD H the lowest point for a 22mm boss connector is 450mm above the invert of the rest bend. I hunted last night for some other restriction, but that does appear to be it.
I could lift a 3x2 and trowel away at the clay until I find the pipe, however this is still at the "all possible on the shelf designs" stage. The low level brick manhole cover could have a 22mm low entry, but that part would be outsourced (paved cover, waterproof pipe insulation, UV proof also above terra firma).
Thanks.