Hello all
I have had an extension built which will have 3 radiators to the big main room, a utility sink and a shower room (ground works, waste, and pipes etc are in)
The builder is not installing the sanitary ware as I will have to save up in order to fit the shower room in a few years time, which he knows.
My question is, should the connecting of the new pipe work to my existing heating and water be considered part of the first fix?
I am wanting to heat the room and connect a washing machine up and generally use the room for years without a working shower room, but he has since told me, 3 months into the build, that he will not be connecting up until I install the shower room.
Your opinions please
 
It depends entirely what was agreed!
If you’d stated that you wished to use the room as a utility for as few years and could it be plumbed for a washing machine and have its radiator connected in - then that’s what should be included.
If you said it was to be a shower room but that was a future project- I would expect h/c supplies to the room and wastes in place (if that was agreed) - but no more than that.

It all comes down to communication
 

Official Sponsors of Plumbers Talk

Reply to the thread, titled "What does First Fix include?" which is posted in UK Plumbers Forums on Plumbers Forums.

We recommend City Plumbing Supplies, BES, and Plumbing Superstore for all plumbing supplies.

Weekly or Monthly Email Digest

Back
Top