Discuss date change for OF terminal clearance to roofs in the Plumbing Jobs | The Job-board area at PlumbersForums.net

Status
Not open for further replies.
K

kirkgas

Right, ladies and gentlemen, obviously I know the answer to this and i just want to give you the chance to prove how clever you are ;):eek:

its only for the oldies, remember when we used to determine OF flue height through roof by the angle of the roof? ie less than 45 degrees you had 600mm pipe through the roof, and more than 45 degrees you had 1000mm through the roof, rather than the 1500mm horizontally or 600mm above ridge,
but what i need is the date of the change, thought i had nothing to do but look in IUP and BS5400-1, but for the life of me i cannot see it, it is for someone classifying on service contract and if installed before the rule change they will be NCS, on thinking about it, if passing flue flow and spillage would we agree that even if the were fitted after the rule change and working peoperly they will still be NCS, but its annoying me that i cant find the date change,
cheers
 
Hi, New terminal locations came in year 2000 as per BS5440-1:2000
Gosh! isn't time flying by.......
 
Last edited:
Hi, New terminal locations came in year 2000 as per BS5440-1:2000
Gosh! isn't time flying by.......

top banana, cheers, (couldnt find any ref in there today, will re-read it properly)
 
Impressed, can't believe it was so long ago. Latest version of BS5440 part 1 is 2008. Does anyone know what changes were made from the 2000 edition?
 
Status
Not open for further replies.

Reply to date change for OF terminal clearance to roofs in the Plumbing Jobs | The Job-board area at PlumbersForums.net

Similar plumbing topics

Hi all. Hope you have all been keeping well. A while back I decided I only wanted to fit one brand of boiler and decided on Viessmann due to...
Replies
9
Views
475
Hello new to the forum so will say thank you in advance to all and any assistance you can provide. background: current boiler installed in...
Replies
20
Views
10K
A number of issues have been raised from a boiler replacement. Boiler not operating and with no pressure. Tile damage Sprawling pipe layout in...
Replies
21
Views
5K
  • Locked
I did a landlord inspection on an open flue gas fire on saturday. Its about 20 years old, never failed an annual inspection before. Passed flue...
Replies
11
Views
83
ed209
E
A
  • Locked
Hi guys With an open flue the minimum distance for a vertical flue terminal through a roof is 1500mm from the apex (or 600mm above ridge). I...